On July 22, the E24 pipe section of the Shenzhen-Zhongshan Bridge underwater tunnel was installed, marking the completion of the installation of all 9 pipe sections on the east side of the tunnel .
So far, a total of 27 pipe sections have been installed, with a total length of 4,207.8 meters.
In late July, the pipe section installation for the west side of the tunnel will start.